Thursday, August 18, 2011

RUSTON SEWER PROJECT

Towm meeting Ruston Sewer Project August 17, 2011 7pm

Moderator was Jerry Morrissette, Town Engineer
Attendance was around 20 Towns people including:
Mayor, Bruce Hopkins
Council persons, Lyle Hardin and Jane Hunt
Former Council Persons Bob Pudlo and Dan Albertson
Town contact person Steve Taylor
Project persons, Jerry Morrissette, Dan Ozier and Charlie Severs.

After a presentation meeting was opened up for questions from the public.
My notes follow.
I&I, inflow and infiltration, storm water into sewer system causes overload at treatment plant in Tacoma is major problem.
Current sewer pipe 4-6 inches not up to code.
Funding for project from USDA (Department of Agriculture)rural development program.
Low interest rate loan over 40 years.
Will be a separate website for sewer project linked from town website (not active yet).
Houses built prior to 1970 need side sewer laterals replaced.
Permit for work available at Town Hall. Fee $90 dollars (lateral to main).
Can do work ahead of time.
Contractor schedule better detail than normal.
Due to railroad permitting some work not completed until August 2012.
J R Rodarte is prime contractor, no laterals.
Will use trenchless technology.
Steve Taylor is contact person.
Cost of lateral $1 thousand dollars to $3 thousand dollars with median at $1,500 dollars.
Cost will vary due to topograpy: trees, stone walls, etc.,
Adapters are available for difficult connections.
Cost on utility bills $5 dollars per month per home owner.
Town has done long range planning for cost reduction.
Timing of rate increase up to the Town Council.
Commercial street patch only no repaving.
Town has aerial map of sewer showing where to conncect.
Some alleys closed two to four weeks.
Garbage collection will be on street until finished.
Steve Taylor made comment time will be shorter than that.
Jerry we have to use worst case to avoid problems.
Alleys at 51st street and Rust Way.
How long will sewer service be out?
Momentarily, up to one hour.
Check website out for details.
Will be given 48 hours notice.
Plumbers responsibilty to know codes.
Questions can be posted on website or contact Steve Taylor during business hours.
Repave 49th street with asphalt.
City of Tacoma replacing main.
No alley in back of 49th street. Access will be limited. Will need to park elsewhere and walk. One lane open with flaggers will limit access to Pearl street.
Could have water problems with winter work.
Completion scheduled for October 2012.
Work has to be done and public patience appreciated.
Different crews may do sections one and three simultaneously.
Comment neighbors may charge five dollars to park in their yard brought laughter from crowd.
Project contact Charlie Severs 360-481-4144.
When it wwas pointed out that was long distance there was talk of getting an 800 number or using email. (Not all residents have computers)

Town of Ruston officials:
Mayor, Bruce Hopkins
Council, Bradley Huson, Jim Hedrick, Deborah Kristovich, Lyle Hardin, Jane Hunt
Attorney, Carol Morris
Planner, Rob White
Clerk/Treasurer, Myriah Mesa
Fire Chief, Don Torbet
Police Chief, Jeremy Kunkel
Electrician, John Parker
Electricial Engineer, Mo Fesharaki
Engineer, Jerry Morrissette
-30-